Aptitude Quiz on Time and Work

1. A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

A.12 days  B.15 days

C.16 days D.18 days




2. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

A.Rs. 375  B.Rs. 400

C.Rs. 600 D.Rs. 800




3. A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

A.20 days B.22 1/2days

C.25 days D.30 days




4. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

A.4 days B.5 days

C.6 days D.7 days




5. A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

A.15 days B.20 days

C.25 days    D.30 days




6. A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?

A.11:30 A.M. B.12 noon

C.12:30 P.M. D.1:00 P.M.




7. A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

A.23 days B.37 days

C.371/2 D.40 days




8. A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

A.5 B.5 1/2

C.6 D.8




9. A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?

A.8 hours B.10 hours

C.12 hours D.24 hours




10. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?

A.35 B.40

C.45            D.50